N. Charlotte Ave. Water Main Replacement Project Traffic Control Plan

N. Charlotte Ave. Water Main Replacement Project Traffic Control Plan

The contractor is scheduled to start on November 5th and anticipated to conclude on December 13th.

Because of some incidences which occurred on N. Charlotte Ave. with other contractors recently, NCDOT has required that we change our traffic control plan from what was originally discussed.  You should expect the following:

1.       A one lane road closure will take place from to 9AM-4PM, Mon-Fri. 

2.       Inbound traffic (southbound lane closed) will be diverted to the outbound lane temporarily until being tapered back into its normal travel path. 

3.       Outbound traffic will be detoured onto Concord Ave. and to Patton Ave. to get back to N. Charlotte Ave. 

4.       All side streets be closed within the work zone, with the exception to W. Phifer St. (west side) since it is a dead end street.  Right turn only signs will be placed on W. Phifer St. (west side). 

Click Traffic Plan for more information.